GATE 2020 Architecture and Planning question: The activity duration, early start, early finish, late start and late finish of the…
The activity duration, early start, early finish, late start and late finish of the three activities ‘P’, ‘Q’ and ‘R’ are shown in the following figure. The independent float of activity ‘Q’ is ______

Show answer
Official answer: 1