GATE 2020 · AR · NAT · 2 marks · Part B1: Architecture › Construction Planning, PERT & CPM

GATE 2020 Architecture and Planning question: The activity duration, early start, early finish, late start and late finish of the…

The activity duration, early start, early finish, late start and late finish of the three activities ‘P’, ‘Q’ and ‘R’ are shown in the following figure. The independent float of activity ‘Q’ is ______

figure

Show answer

Official answer: 1