GATE 2020 set1 · ME · MCQ · 2 marks · Industrial Engineering › Production Planning & Scheduling

GATE 2020 set1 Mechanical Engineering question: For an assembly line, the production rate was 4 pieces per hour and the average…

For an assembly line, the production rate was 4 pieces per hour and the average processing time was 60 minutes. The WIP inventory was calculated. Now, the production rate is kept the same, and the average processing time is brought down by 30 percent. As a result of this change in the processing time, the WIP inventory

  1. (A)

    decreases by 25%

  2. (B)

    increases by 25%

  3. (C)

    decreases by 30%

  4. (D)

    increases by 30%

Show answer

Official answer: C