GATE Assistant

Past questions › Mechanical Engineering › GATE 2020 set2

GATE 2020 set2 · ME · NAT · 1 mark · Industrial Engineering › PERT & CPM

GATE 2020 set2 Mechanical Engineering question: Consider the following network of activities, with each activity named A–L , illustrated…

Consider the following network of activities, with each activity named A–L, illustrated in the nodes of the network.

figure

The number of hours required for each activity is shown alongside the nodes. The slack on the activity L, is ________ hours.

Show answer

Official answer: 2

Practise this question with exam-style marking

Discussion

No discussion yet.

Join the discussion