GATE 2020 Petroleum Engineering question: A drawdown test is conducted at a constant flow rate in an oil well for a reservoir with…

A drawdown test is conducted at a constant flow rate in an oil well for a reservoir with constant compressibility. Which one of the following is valid for semi steady state condition?

  1. (A)

    Rate of pressure change at the wellbore is less than that at the boundary.

  2. (B)

    The effect of the outer boundary of the reservoir is felt at the wellbore.

  3. (C)

    Reservoir permeability does not affect the wellbore pressure.

  4. (D)

    Pressure in the reservoir does not change with time.

Show answer

Official answer: B