GATE Assistant

Past questions › Petroleum Engineering › GATE 2020

GATE 2020 · PE · NAT · 2 marks · Petroleum Production Operations › Multiphase Flow & Flow Assurance

GATE 2020 Petroleum Engineering question: The slip velocity for a gas-liquid flow in a vertical production well is 0.1 m/s. The…

The slip velocity for a gas-liquid flow in a vertical production well is 0.1 m/s. The superficial velocity of each of the phases is 0.1 m/s. The fractional hold-up of the gas phase (rounded off to two decimal places) is _________.

Show answer

Official answer: 0.36 to 0.4

Practise this question with exam-style marking

Discussion

No discussion yet.

Join the discussion