GATE 2020 Production and Industrial Engineering question: A project consists of seven activities as listed in the table. The time required for…
A project consists of seven activities as listed in the table. The time required for each activity and its immediate predecessor(s) are also given.
| Activity | Time required (in weeks) | Immediate Predecessor(s) |
|---|---|---|
| P | 7 | - |
| Q | 4 | - |
| R | 2 | Q |
| S | 11 | P |
| T | 9 | P, R |
| U | 9 | Q |
| V | 4 | T, U |
The project completion time using Critical Path Method (CPM) in weeks is ___________.