GATE Assistant

Past questions › Production and Industrial Engineering › GATE 2020

GATE 2020 · PI · NAT · 2 marks · Operations research and Operations management › Project Management: CPM & PERT

GATE 2020 Production and Industrial Engineering question: A project consists of seven activities as listed in the table. The time required for…

A project consists of seven activities as listed in the table. The time required for each activity and its immediate predecessor(s) are also given.

Activity Time required (in weeks) Immediate Predecessor(s)
P 7 -
Q 4 -
R 2 Q
S 11 P
T 9 P, R
U 9 Q
V 4 T, U

The project completion time using Critical Path Method (CPM) in weeks is ___________.

Show answer

This question is in an all-India live mock that is open now. Its answer appears here when the mock closes.

Practise this question with exam-style marking