GATE 2021 · AR · MCQ · 1 mark · Part B2: Planning › Sanitation, Sewerage & Wastewater

GATE 2021 Architecture and Planning question: A waste water pipe connecting two inspection chambers (IC) is laid at a slope of 1:200.…

A waste water pipe connecting two inspection chambers (IC) is laid at a slope of 1:200. The Invert Level of the starting IC is -450 mm. The Invert level of the second pit at a distance of 40 m from the first IC is

  1. (A)

    -650 mm.

  2. (B)

    -200 mm.

  3. (C)

    -250 mm.

  4. (D)

    -550 mm.

Show answer

Official answer: A