GATE 2021 Architecture and Planning question: The two components for measuring time of concentration for storm water are

The two components for measuring time of concentration for storm water are

  1. (A)

    overland flow time and retention time.

  2. (B)

    overland flow time and gutter flow time.

  3. (C)

    detention time and gutter flow time.

  4. (D)

    retention time and inlet time.