GATE 2021 · AR · MSQ · 2 marks · Part B2: Planning › Solid Waste Management
GATE 2021 Architecture and Planning question: As per the Solid Waste Management Rules 2016, which among the following are ‘Duties of…
As per the Solid Waste Management Rules 2016, which among the following are ‘Duties of waste generators’?
- (A)
Segregate and store waste generated in four separate streams namely, combustible, non-combustible, organic and domestic hazardous waste
- (B)
Store construction and demolition waste separately within own premise before disposal
- (C)
All waste generator shall pay user fee for solid waste management
- (D)
Compost horticulture waste and garden waste separately within own premise
Show answer
Official answer: B,C