GATE 2021 Architecture and Planning question: A building is constructed on a plot measuring 70 m × 40 m. The utilized FAR of the…
A building is constructed on a plot measuring 70 m × 40 m. The utilized FAR of the building is 1.5. An energy audit team found that the average monthly electricity bill of the building is INR 2,94,000. The unit cost of the electricity is INR 7. The Building Energy Index is __________ kW-hr/m/year. [in integer]
Show answer
Official answer: 120