GATE 2021 · AR · NAT · 2 marks · Part B1: Architecture › Construction Planning, PERT & CPM

GATE 2021 Architecture and Planning question: A construction project consists of following five activities. The immediate successor…

A construction project consists of following five activities. The immediate successor activity relationship and duration of each activity are mentioned in the table below.

Activity Immediate Successor Activity Duration (Weeks)
P R 2
Q R and S 4
R T 5
S – 6
T – 3

The total duration of the project is _______ weeks. [in integer]

Show answer

Official answer: 12