GATE 2021 set1 Civil Engineering question: The direct and indirect costs estimated by a contractor for bidding a project is ₹160000…

The direct and indirect costs estimated by a contractor for bidding a project is ₹160000 and ₹20000 respectively. If the mark up applied is 10% of the bid price, the quoted price (in ₹) of the contractor is

  1. (A)

    200000

  2. (B)

    198000

  3. (C)

    196000

  4. (D)

    182000

Show answer

Official answer: A