Contractor X is developing his bidding strategy against Contractor Y. The ratio of Y’s bid price to X’s cost for the 30 previous bids in which Contractor X has competed against Contractor Y is given in the Table
| Ratio of Y’s bid price to X’s cost | Number of bids |
|---|---|
| 1.02 | 6 |
| 1.04 | 12 |
| 1.06 | 3 |
| 1.10 | 6 |
| 1.12 | 3 |
Based on the bidding behaviour of the Contractor Y, the probability of winning against Contractor Y at a mark up of 8% for the next project is
Show answer
Official answer: B