GATE Assistant

Past questions › Civil Engineering › GATE 2021 set2

GATE 2021 set2 · CE · NAT · 2 marks · Structural Engineering › Construction Materials & Management

GATE 2021 set2 Civil Engineering question: The activity details for a small project are given in the Table. Activity Duration…

The activity details for a small project are given in the Table.

Activity Duration (days) Depends on
A 6 -
B 10 A
C 14 A
D 8 B
E 12 C
F 8 C
G 16 D, E
H 8 F, G
K 2 B
L 5 G, K

The total time (in days, in integer) for project completion is ____________

Show answer

Official answer: 56