GATE 2021 set2 Civil Engineering question: The activity details for a small project are given in the Table. Activity Duration…
The activity details for a small project are given in the Table.
| Activity | Duration (days) | Depends on |
|---|---|---|
| A | 6 | - |
| B | 10 | A |
| C | 14 | A |
| D | 8 | B |
| E | 12 | C |
| F | 8 | C |
| G | 16 | D, E |
| H | 8 | F, G |
| K | 2 | B |
| L | 5 | G, K |
The total time (in days, in integer) for project completion is ____________
Show answer
Official answer: 56