GATE 2021 Environmental Science and Engineering question: A sewage treatment plant (STP) receives sewage at a flow rate of 20000 m 3 per day. The…
A sewage treatment plant (STP) receives sewage at a flow rate of 20000 m per day. The sewage has 200 mg/L of suspended solids. Assume 60 % suspended solids are removed in the primary clarifier. The underflow (i.e. sludge) removed from the clarifier contains 5 % solids (by weight).
The daily volume of the sludge generated will be
____________ m per day.
Assume sludge density = 1000 kg/m.
Show answer
Official answer: A