GATE 2021 set1 · ME · MCQ · 2 marks · Industrial Engineering › Production Planning & Scheduling

GATE 2021 set1 Mechanical Engineering question: A set of jobs A, B, C, D, E, F, G, H arrive at time t = 0 for processing on turning and…

A set of jobs A, B, C, D, E, F, G, H arrive at time for processing on turning and grinding machines. Each job needs to be processed in sequence – first on the turning machine and second on the grinding machine, and the grinding must occur immediately after turning. The processing times of the jobs are given below.

Job A B C D E F G H
Turning (minutes) 2 4 8 9 7 6 5 10
Grinding (minutes) 6 1 3 7 9 5 2 4

If the makespan is to be minimized, then the optimal sequence in which these jobs must be processed on the turning and grinding machines is

  1. (A)

    A-E-D-F-H-C-G-B

  2. (B)

    A-D-E-F-H-C-G-B

  3. (C)

    G-E-D-F-H-C-A-B

  4. (D)

    B-G-C-H-F-D-E-A

Show answer

Official answer: A

Practise this question with exam-style marking

Discussion