GATE 2021 set1 Mechanical Engineering question: Activities A, B, C and D form the critical path for a project with a PERT network. The…
Activities A, B, C and D form the critical path for a project with a PERT network. The means and variances of the activity duration for each activity are given below. All activity durations follow the Gaussian (normal) distribution, and are independent of each other.
| Activity | A | B | C | D |
|---|---|---|---|---|
| Mean (days) | 6 | 11 | 8 | 15 |
| Variance (days) | 4 | 9 | 4 | 9 |
The probability that the project will be completed within 40 days is __________ (round off to two decimal places).
(Note: Probability is a number between 0 and 1).
Show answer
Official answer: 0.5