A PERT network has 9 activities on its critical path. The standard deviation of each activity on the critical path is 3. The standard deviation of the critical path is

  1. (A)

    3

  2. (B)

    9

  3. (C)

    27

  4. (D)

    81

Show answer

Official answer: B