GATE 2021 set2 · ME · MCQ · 2 marks · Industrial Engineering › Production Planning & Scheduling

GATE 2021 set2 Mechanical Engineering question: A factory produces m (i = 1, 2, ..., m) products, each of which requires processing on n…

A factory produces () products, each of which requires processing on () workstations. Let be the amount of processing time that one unit of the product requires on the workstation. Let the revenue from selling one unit of the product be and be the holding cost per unit per time period for the product. The planning horizon consists of () time periods. The minimum demand that must be satisfied in time period is , and the capacity of the workstation in time period is . Consider the aggregate planning formulation below, with decision variables (amount of product sold in time period ), (amount of product manufactured in time period ) and (amount of product held in inventory at the end of time period .

subject to

capacity constraint

inventory balance constraint

The capacity constraints and inventory balance constraints for this formulation are

  1. (A)

    and

  2. (B)

    and

  3. (C)

    and

  4. (D)

    and

Show answer

Official answer: A