GATE 2021 set2 · ME · NAT · 2 marks · Industrial Engineering › Forecasting

GATE 2021 set2 Mechanical Engineering question: The demand and forecast of an item for five months are given in the table. Month Demand…

The demand and forecast of an item for five months are given in the table.

Month Demand Forecast
April 225 200
May 220 240
June 285 300
July 290 270
August 250 230

The Mean Absolute Percent Error (MAPE) in the forecast is ___________ %
(round off to two decimal places)

Show answer

Official answer: 6 to 10