GATE 2021 Mining Engineering question: The hydraulic sand stowing pipeline layout should be such that

The hydraulic sand stowing pipeline layout should be such that

  1. (A)

    the geometric profile must coincide with the hydraulic gradient line.

  2. (B)

    the hydraulic profile should always be below the hydraulic gradient line.

  3. (C)

    the hydraulic profile should always be above the hydraulic gradient line.

  4. (D)

    the geometric profile should always be above the hydraulic gradient line.

Show answer

Official answer: B