GATE 2021 · MN · NAT · 1 mark · Surface Environment, Mine Ventilation and Underground Hazards › Noise, Land Reclamation & EIA

GATE 2021 Mining Engineering question: In Battle Environmental Evaluation System (BEES) of Environmental Impact Assessment…

In Battle Environmental Evaluation System (BEES) of Environmental Impact Assessment (EIA), "air pollution" has a Parameter Importance Unit (PIU) value of 52. The Environmental Quality (EQ) score of a project with respect to air pollution was 0.8 before the project implementation and it becomes 0.6 after the project implementation. The difference in the "Environmental Impact Unit (EIU)", before and after the project implementation is______.

[round off to 2 decimal places]

Show answer

Official answer: 10.4