GATE 2021 · MN · MCQ · 2 marks · Mining Methods and Machinery › Wire Ropes, Haulages & Conveyors

GATE 2021 Mining Engineering question: In a bord and pillar panel six shuttle cars, each of 10 tonne capacity, are deployed to…

In a bord and pillar panel six shuttle cars, each of 10 tonne capacity, are deployed to transport coal produced by two continuous miners to a belt conveyor. Each shuttle car on an average carries 80% of its rated capacity and makes 7 round trips in an hour. The belt conveyor has a capacity such that the effective material cross section area is of 0.09 m and runs at a speed 1.1 m/s. The broken coal has a bulk density of 1.2 tonne/m. The ratio between the production and the capacity of the belt conveyor, in percent is

  1. (A)

    65.46

  2. (B)

    71.42

  3. (C)

    78.56

  4. (D)

    82.46

Show answer

Official answer: C