GATE Assistant

Past questions › Mining Engineering › GATE 2021

GATE 2021 · MN · NAT · 2 marks · Mining Geology, Mine Development and Surveying › Levelling, Tacheometry & Triangulation

GATE 2021 Mining Engineering question: On an old plan of scale 1:1000, leasehold area of a mine is now measured as 802 cm 2…

On an old plan of scale 1:1000, leasehold area of a mine is now measured as 802 cm using a planimeter. The plan is found to have shrunk, such that the original line of 10 cm is now measured as 9.8 cm on the plan. True lease hold mine area, in m, is _______. [round off to the nearest integer]

Show answer

Official answer: 83450 to 83550

Practise this question with exam-style marking

Discussion

No discussion yet.

Join the discussion