GATE 2021 Mining Engineering question: Ore is hoisted from 620 m depth using a single skip of 7 tonne pay load. The skip…

Ore is hoisted from 620 m depth using a single skip of 7 tonne pay load. The skip winding system has constant acceleration/deceleration of 1 m/s and a constant speed of 10 m/s. The skip loading time and unloading time are 120 s and 60 s, respectively. Considering the overall utilization of the skip as 70 %, the maximum daily capacity of the winding system, in tonne, is ______. [round off to the nearest integer]

Show answer

Official answer: 1250 to 1350