GATE 2021 Mining Engineering question: A project network consists of the following activities Activity Immediate predecessors…

A project network consists of the following activities

Activity Immediate predecessors Duration (days)
A -- 3
B -- 4
C A, B 5
D B 6
E D 7
F C, E 8
G D 9
H F, G X

If the project completion time is 30 days, then the value of 'X', in days, is_______.

[in integer]

Show answer

Official answer: 5