GATE 2021 Petroleum Engineering question: During a drilling operation, kick occurs if

During a drilling operation, kick occurs if

  1. (A)

    the shear ram in the Blow Out Preventer (BOP) does not work.

  2. (B)

    the formation pressure is equal to the drilling fluid pressure.

  3. (C)

    the volume of the mud used to fill the hole is less than that of the pipe being pulled out.

  4. (D)

    the formation pressure is more than the drilling fluid pressure.

Show answer

Official answer: C,D or D