Select the CORRECT statements from the following.
Well testing operations on a typical crude oil reservoir
- (A)
do not measure rock and fluid properties of the reservoir when the well is flowing or shut-in.
- (B)
measure variation in pressure response of the reservoir with time when the well is flowing or shut-in.
- (C)
measure productivity index and partial well completion.
- (D)
do not measure length and conductivity of hydraulic fractures.
Show answer
Official answer: B,C or A,B,C