GATE 2021 Petroleum Engineering question: A productivity test conducted on a crude oil well indicates a stabilized flow rate of…

A productivity test conducted on a crude oil well indicates a stabilized flow rate of 150 STB/day (water-free oil production) at a bottom-hole flowing pressure of 935 psig. After shutting the well for 24 hours, the bottom-hole pressure reached a static value of 1250 psig.

The Absolute Open Flow (AOF) potential of the well is ____________ STB/day.

Show answer

Official answer: 580 to 610