GATE 2021 Petroleum Engineering question: During drilling, a well is damaged out to a radial distance of 5 ft from the periphery…

During drilling, a well is damaged out to a radial distance of 5 ft from the periphery of the wellbore so that the permeability within the damaged zone is reduced to 1/50th of the undamaged effective permeability. After completion, the well is stimulated so that the permeability out to a radial distance of 15 ft from the periphery of the wellbore is increased to twenty times the permeability of the undamaged zone.

The radial inflow equation for stabilized flow conditions under semi-steady state conditions is given by

where is effective pressure, is flowing bottom-hole pressure, is flow-rate, is viscosity, is average effective permeability, is reservoir thickness, is drainage radius, is wellbore radius and is skin factor.

If = 0.5 ft and = 500 ft, then the increase in Productivity Index ratio is ____________ (round off to one decimal place).

Show answer

Official answer: 32 to 42