GATE 2021 Production and Industrial Engineering question: Which one of the following is NOT a measure of forecast error?

Which one of the following is NOT a measure of forecast error?

  1. (A)

    Mean absolute deviation (MAD)

  2. (B)

    Mean squared error (MSE)

  3. (C)

    Mean absolute percent error (MAPE)

  4. (D)

    Mean sum product error (MSPE)

Show answer

Official answer: D