GATE 2021 · PI · MCQ · 2 marks · Quality and Reliability › Statistical Quality Control

GATE 2021 Production and Industrial Engineering question: For a given process control chart, there are four rules for determining out-of-control…

For a given process control chart, there are four rules for determining out-of-control state of the process which are being used simultaneously. The probability of Type-I error for the four rules are 0.005, 0.02, 0.03, and 0.05. Assuming independence of the rules, the probability of overall Type-I error when all the four rules are used simultaneously is

  1. (A)

    0.101

  2. (B)

    0.201

  3. (C)

    0.001

  4. (D)

    0.301

Show answer

Official answer: A