GATE 2021 Production and Industrial Engineering question: A project consists of eight activities. The time required for each activity and its…
A project consists of eight activities. The time required for each activity and its immediate predecessor(s) are given in the table below.
| Activity | Activity time (in days) | Immediate predecessor(s) |
|---|---|---|
| A | 2 | - |
| B | 3 | - |
| C | 2 | A |
| D | 4 | A, B |
| E | 4 | C |
| F | 3 | C |
| G | X | D, E |
| H | 2 | F, G |
If the project completion time using critical path method (CPM) is 15 days, then the value of X (in days) is ________. [in integer]
Show answer
Official answer: 5