GATE Assistant

Past questions › Production and Industrial Engineering › GATE 2021

GATE 2021 · PI · NAT · 2 marks · Operations research and Operations management › Project Management: CPM & PERT

GATE 2021 Production and Industrial Engineering question: A project consists of eight activities. The time required for each activity and its…

A project consists of eight activities. The time required for each activity and its immediate predecessor(s) are given in the table below.

Activity Activity time (in days) Immediate predecessor(s)
A 2 -
B 3 -
C 2 A
D 4 A, B
E 4 C
F 3 C
G X D, E
H 2 F, G

If the project completion time using critical path method (CPM) is 15 days, then the value of X (in days) is ________. [in integer]

Show answer

Official answer: 5

Practise this question with exam-style marking

Discussion

No discussion yet.

Join the discussion