GATE 2021 Production and Industrial Engineering question: In an arc welding process, the DC power source characteristic is linear with an open…

In an arc welding process, the DC power source characteristic is linear with an open circuit voltage of 60 V and short circuit current of 600 A. The heat required for melting a metal during the welding is 10 J/mm, and the heat transfer and melting efficiencies are 80% and 25%, respectively. If the weld cross-sectional area of 20 mm is made using the maximum arc power, then the required welding speed in mm/s is ________. [round off to one decimal place]

Show answer

Official answer: 8.8 to 9.2