GATE 2022 Architecture and Planning question: The activity duration, early start, early finish, late start, and late finish (in weeks)…

The activity duration, early start, early finish, late start, and late finish (in weeks) for activities P, Q, R, and S are shown in the following figure. The interfering float of activity R (in weeks, in integer) is ___________.

figure

Show answer

Official answer: 6