GATE 2022 set1 Civil Engineering question: The project activities are given in the following table along with the duration and…

The project activities are given in the following table along with the duration and dependency.

Activities Duration (days) Depends on
P 10 -
Q 12 -
R 5 P
S 10 Q
T 10 P, Q

Which one of the following combinations is correct?

  1. (A)

    Total duration of the project = 22 days, Critical path is Q S

  2. (B)

    Total duration of the project = 20 days, Critical path is Q T

  3. (C)

    Total duration of the project = 22 days, Critical path is P T

  4. (D)

    Total duration of the project = 20 days, Critical path is P R

Show answer

Official answer: A