The project activities are given in the following table along with the duration and dependency.
| Activities |
Duration (days) |
Depends on |
| P |
10 |
- |
| Q |
12 |
- |
| R |
5 |
P |
| S |
10 |
Q |
| T |
10 |
P, Q |
Which one of the following combinations is correct?
- (A)
Total duration of the project = 22 days, Critical path is Q → S
- (B)
Total duration of the project = 20 days, Critical path is Q → T
- (C)
Total duration of the project = 22 days, Critical path is P → T
- (D)
Total duration of the project = 20 days, Critical path is P → R
Show answer
Official answer: A