GATE 2022 set1 · CE · NAT · 2 marks · Transportation Engineering › Traffic Engineering

GATE 2022 set1 Civil Engineering question: A two-phase signalized intersection is designed with a cycle time of 100 s. The amber…

A two-phase signalized intersection is designed with a cycle time of 100 s. The amber and red times for each phase are 4 s and 50 s, respectively. If the total lost time per phase due to start-up and clearance is 2 s, the effective green time of each phase is ______ s. (in integer)

Show answer

Official answer: 48