GATE 2022 set2 Civil Engineering question: A flood control structure having an expected life of n years is designed by considering…

A flood control structure having an expected life of years is designed by considering a flood of return period years. When , and , the structure’s hydrologic risk of failure in percentage is ______. (round off to one decimal place)

Show answer

Official answer: 63 to 63.5