GATE 2022 set2 Civil Engineering question: The activities of a project are given in the following table along with their durations…

The activities of a project are given in the following table along with their durations and dependency.

Activities Duration (days) Depends on
A 10 -
B 12 -
C 5 A
D 14 B
E 10 B, C

The total float of the activity E (in days) is ________. (in integer)

Show answer

Official answer: 1