GATE 2022 set2 Mechanical Engineering question: Parts P1-P7 are machined first on a milling machine and then polished at a separate…
Parts P1-P7 are machined first on a milling machine and then polished at a separate machine. Using the information in the following table, the minimum total completion time required for carrying out both the operations for all 7 parts is ___________ hours.
| Part | Milling (hours) | Polishing (hours) |
|---|---|---|
| P1 | 8 | 6 |
| P2 | 3 | 2 |
| P3 | 3 | 4 |
| P4 | 4 | 6 |
| P5 | 5 | 7 |
| P6 | 6 | 4 |
| P7 | 2 | 1 |
Show answer
Official answer: B