Parts P1-P7 are machined first on a milling machine and then polished at a separate machine. Using the information in the following table, the minimum total completion time required for carrying out both the operations for all 7 parts is ___________ hours.

Part Milling (hours) Polishing (hours)
P1 8 6
P2 3 2
P3 3 4
P4 4 6
P5 5 7
P6 6 4
P7 2 1
  1. (A)

    31

  2. (B)

    33

  3. (C)

    30

  4. (D)

    32

Show answer

Official answer: B