GATE 2022 set2 Mechanical Engineering question: A project consists of five activities (A, B, C, D and E). The duration of each activity…

A project consists of five activities (A, B, C, D and E). The duration of each activity follows beta distribution. The three time estimates (in weeks) of each activity and immediate predecessor(s) are listed in the table. The expected time of the project completion is __________ weeks (in integer).

Activity Optimistic time Most likely time Pessimistic time Immediate predecessor(s)
A 4 5 6 None
B 1 3 5 A
C 1 2 3 A
D 2 4 6 C
E 3 4 5 B, D

The column group heading above the first three time columns reads "Time estimates (in weeks)".

Show answer

Official answer: 15