GATE 2022 Mining Engineering question: The bottom section of a stoping block has dimensions 200 m × 40 m. If the modified RMR…

The bottom section of a stoping block has dimensions 200 m × 40 m. If the modified RMR of rock mass is 50, the appropriate method of mining on the basis of Laubscher’s chart in the figure is

figure

  1. (A)

    Shrinkage stoping

  2. (B)

    Cut and fill

  3. (C)

    Block Caving

  4. (D)

    Sublevel stoping

Show answer

Official answer: B