A coal mining company examines the option of buying two types of dumpers with the following details.

Parameter Type-1 Type-2 Constraints
Capital cost per dumper (in ₹ crore) 3.0 4.0 Maximum capital available for purchasing is ₹120 crore
Capacity in tonne 40 50 Minimum daily tonnage to be hauled is 31,000
Daily trips for each dumper 20 20
Operating cost (in ₹) per tonne 300.0 200.0

In order to minimize the operating cost, the optimum fleet of dumpers of Type-1 and Type-2, respectively are

  1. (A)

    20, 15

  2. (B)

    0, 30

  3. (C)

    0, 31

  4. (D)

    40, 0

Show answer

Official answer: A