GATE 2022 · MN · NAT · 2 marks · Geomechanics and Ground Control › Pillar & Support Design

GATE 2022 Mining Engineering question: The extraction ratio during development of a bord and pillar panel is 0.15 in a flat…

The extraction ratio during development of a bord and pillar panel is 0.15 in a flat coal seam. The panel is further extracted by widening the galleries, and the extraction ratio changes to 0.25. The percentage change in pillar stress, considering tributary area method, is_______. (round off to two decimal places)

Show answer

Official answer: 13 to 14