GATE 2022 Mining Engineering question: In a surface mine bench, overburden is removed by the shovel-dumper combination. For the…

In a surface mine bench, overburden is removed by the shovel-dumper combination. For the dumper:

Time required at the loading station : 3.0 min
Time required at the unloading station : 1.0 min
Distance between loading and unloading stations : 4.5 km
Average speed during loaded travel : 12.0 km/hr
Average speed during empty travel : 18.0 km/hr

Minimum number of dumpers required to avoid idle time of the shovel, is _______. (in integer)

Show answer

Official answer: 14