GATE 2022 Petroleum Engineering question: The drill pipes and drill collars with a combined length of 2500 m are held on the hook…
The drill pipes and drill collars with a combined length of 2500 m are held on the hook without rotation and mud flow. The specific gravity of the mud in the annulus is 1.5 and that inside the drill string is 1.4. The material density of the drill pipe and drill collar is 7850 kg/m. The specifications of drill pipes and drill collars are given below.
| Specification | Drill pipe | Drill collar |
|---|---|---|
| Length (m) | 2000 | 500 |
| Inside diameter (m) | 0.106 | 0.127 |
| Outside diameter (m) | 0.156 | 0.406 |
| Mass per unit length (kg/m) | 30 | 870 |
The overall weight acting on the hook is _______ kN (rounded off to two decimal places).
Show answer
Official answer: 3870 to 4070