GATE 2022 Production and Industrial Engineering question: A project comprises of seven activities. The expected durations of activities and their…
A project comprises of seven activities. The expected durations of activities and their variances are as follows:
| Activity | Expected duration (minute) | Variance (minute) |
|---|---|---|
| A | 4 | 1 |
| B | 5 | 1 |
| C | 4 | 1 |
| D | 1 | 0 |
| E | 7 | 4 |
| F | 6 | 1 |
| G | 8 | 4 |
The critical path consists of activities B, E and G. The standard deviation (in minute) of the project duration is______________. [round off to two decimal places]
Show answer
Official answer: 2.9 to 3.1