GATE 2022 Production and Industrial Engineering question: A project comprises of seven activities. The expected durations of activities and their…

A project comprises of seven activities. The expected durations of activities and their variances are as follows:

Activity Expected duration (minute) Variance (minute)
A 4 1
B 5 1
C 4 1
D 1 0
E 7 4
F 6 1
G 8 4

The critical path consists of activities B, E and G. The standard deviation (in minute) of the project duration is______________. [round off to two decimal places]

Show answer

Official answer: 2.9 to 3.1