GATE 2022 Production and Industrial Engineering question: A time study engineer recorded the cycle time (in minute) for machining of a component.…
A time study engineer recorded the cycle time (in minute) for machining of a component. The recorded time study data is provided in the table. The performance rating of the worker is 110%. The standard time for machining (in minute) the component by assuming 10% allowance is ______________. [round off to nearest integer]
Time study data
| Cycle time (minute) | Frequency |
|---|---|
| 42 | 1 |
| 43 | 2 |
| 44 | 3 |
| 45 | 2 |
| 46 | 1 |
Show answer
Official answer: 53 to 54