GATE 2022 · PI · NAT · 2 marks · Industrial Engineering › Method Study & Work Measurement

GATE 2022 Production and Industrial Engineering question: A time study engineer recorded the cycle time (in minute) for machining of a component.…

A time study engineer recorded the cycle time (in minute) for machining of a component. The recorded time study data is provided in the table. The performance rating of the worker is 110%. The standard time for machining (in minute) the component by assuming 10% allowance is ______________. [round off to nearest integer]

Time study data

Cycle time (minute) Frequency
42 1
43 2
44 3
45 2
46 1
Show answer

Official answer: 53 to 54