GATE 2022 Engineering Sciences question: In a canning industry, the total process time (F 0) was calculated as 3 min. If each can…
In a canning industry, the total process time () was calculated as 3 min. If each can contains 20 spores having decimal reduction time of 1.6 min, the probability of spoilage would be ______ in 100 cans (round off to the nearest integer).
Show answer
Official answer: 25 to 28