GATE 2023 Agricultural Engineering question: It is planned to provide irrigation in a crop field having field capacity and permanent…
It is planned to provide irrigation in a crop field having field capacity and permanent wilting point of the soil as 0.21 cm cm and 0.09 cm cm, respectively. The crop root zone depth is 0.90 m. The growing period of this crop is 1st January to 31st March, during which the observed reference evapotranspiration (ET), effective rainfall (P) and crop coefficients (K) are listed below. Considering management allowable deficit (MAD) for this crop as 50%, the average irrigation interval during the growing period in days is
| Month | January | February | March |
|---|---|---|---|
| ET (mm day) | 11 | 12 | 14 |
| P (mm month) | 8 | 25 | 27 |
| K | 0.80 | 1.10 | 1.15 |
Show answer
Official answer: B